Project Update January 2024

Construction is moving well this month with the completion of the 33rd floor slab pours and associated columns. Window installations have been completed on L20 and are expected to progress quickly. Precast installation has been progressing well with panels currently being installed on the East elevation. All necessary overhead protection and hoarding has been installed and we ask all pedestrians to continue to exercise caution moving forward. Formwork is still the primary activity on site and residents are asked to continue being mindful of the ongoing concrete and rebar deliveries along Saint Nicholas St. and Wellesley.

Happy New Year from the Centrecourt Team!

Additional Info:
24/7 Hotline Number: 1-855-783-2584
Project Site Supervisor Info: 416-669-9767
Email contact for general inquiries: info@centrecourt.com
Permitted Working Hours:
Monday to Friday, 7:00am to 10:00pm
Saturday, 9:00am to 10:00pm
After 7:00pm, only concrete finishing power floats

Jan 3, 2024