Project Updates

Project Update May 2024

Project Update May 2024

Construction is progressing this month with the completion of the 50th floor slab pours and associated columns. Window installations have been completed on L36 on the tower as well as window installation also being completed on the podium levels. All necessary...

Project Update April 2024

Project Update April 2024

Construction is moving well this month with the completion of the 46th floor slab pours and associated columns. Window installations have been completed on L31 and  windows are also currently being installed on the podium levels. All necessary overhead protection and...

Project Update March 2024

Project Update March 2024

Construction is moving well this month with the completion of the 42nd floor slab pours and associated columns. Window installations have been completed on L26 and with the completion Precast panel installation, windows are also currently being installed on L2,L3...

Project Update February 2024

Project Update February 2024

Construction is moving well this month with the completion of the 37th floor slab pours and associated columns. Window installations have been completed on L22 and with the completion Precast panel installation, windows are also currently being installed on L2. All...

Project Update January 2024

Project Update January 2024

Construction is moving well this month with the completion of the 33rd floor slab pours and associated columns. Window installations have been completed on L20 and are expected to progress quickly. Precast installation has been progressing well with panels currently...

Project Update – December 2023

Project Update – December 2023

Construction is moving well this month with the completion of the 30th floor slab pours and associated columns. Window installations have been completed on L16 and are expected to progress quickly. Precast installation has been progressing well on the South, West and...

Project Update – November 2023

Project Update – November 2023

Construction is moving well this month with the completion of the 26th floor slab pours and associated columns, while proceeding to form and pour the 27th floor slab. Window installations have been completed on L11 and are expected to progress quickly. Precast...

Project Update – October 2023

Project Update – October 2023

Construction is moving well this month with the completion of the 20th floor slab pours and associated columns, while proceeding to form and pour the 21st floor slab. Window installations have been completed on L8 and are expected to progress quickly. Heritage...

Project Update – September 2023

Project Update – September 2023

Construction is progressing well this month with the completion of the 15th floor slab pours and associated columns, while proceeding to form and pour the 16th floor slab. Heritage restoration is continuing this month with work being completed on 586 Yonge street,...

Project Update – August 2023

Project Update – August 2023

Construction is progressing well this month with the completion of the 10th floor slab pours and associated columns, while proceeding to form and pour the 11th floor slab. Heritage restoration is continuing this month with work being completed on 586 Yonge street,...

8 Wellesley St W, Toronto, ON M4Y 1E7