Project Update March 2024

Construction is moving well this month with the completion of the 42nd floor slab pours and associated columns. Window installations have been completed on L26 and with the completion Precast panel installation, windows are also currently being installed on L2,L3 & L4. All necessary overhead protection and hoarding has been installed and we ask all pedestrians to continue to exercise caution moving forward. Formwork is still the primary activity on site and residents are asked to continue being mindful of the ongoing concrete and rebar deliveries along Saint Nicholas St. and Wellesley.

Additional Info:
24/7 Hotline Number: 1-855-783-2584
Project Site Supervisor Info: 416-669-9767
Email contact for general inquiries: info@centrecourt.com
Permitted Working Hours:
Monday to Friday, 7:00am to 10:00pm
Saturday, 9:00am to 10:00pm
After 7:00pm, only concrete finishing power floats

Mar 4, 2024