Project Updates

Project Update November 2024
Construction is progressing well this month with the final Window installations for the roof nearing completion. We are continuing progress with the finishing of our suites and all Amenity spaces. During this period all nearby residents are asked to continue being...

Project Update October 2024
Construction is progressing well this month with the completion of the final miscellaneous pours for the mechanical penthouse levels. Window installations for the residential floors and steel installation on the roof have also been completed. We are rapidly progress...

Project Update September 2024
Construction is progressing well this month with the completion of the roof pours with a few miscellaneous pours outstanding. Window installations have been completed on L50 on the tower. Roof steel installation has begun and is expected to be completed this month....

Project Update August 2024
Construction is progressing this month with the completion of the Roof Pours Window installations have been completed on L49 on the tower. Completion of the Roof steel is sent to begin this month. All necessary overhead protection and hoarding has been installed and...

Project Update July 2024
Construction is progressing this month with the completion of the both the lower and mechanical penthouse level pours. Window installations have been completed on L45 on the tower. Formwork is still the primary activity on site, with focus on completing the Roof...

Project Update June 2024
Construction is progressing this month with the completion of the final residential concrete pours on the 55th floor. Window installations have been completed on L41 on the tower. Formwork is still the primary activity on site, with focus on completing the Mechanical...

Project Update May 2024
Construction is progressing this month with the completion of the 50th floor slab pours and associated columns. Window installations have been completed on L36 on the tower as well as window installation also being completed on the podium levels. All necessary...

Project Update April 2024
Construction is moving well this month with the completion of the 46th floor slab pours and associated columns. Window installations have been completed on L31 and windows are also currently being installed on the podium levels. All necessary overhead protection and...

Project Update March 2024
Construction is moving well this month with the completion of the 42nd floor slab pours and associated columns. Window installations have been completed on L26 and with the completion Precast panel installation, windows are also currently being installed on L2,L3...

Project Update February 2024
Construction is moving well this month with the completion of the 37th floor slab pours and associated columns. Window installations have been completed on L22 and with the completion Precast panel installation, windows are also currently being installed on L2. All...